curl release procedure - how to do a release
============================================
[in the source code repo]
in the source code repo
-----------------------
- edit RELEASE-NOTES to be accurate
- edit `RELEASE-NOTES` to be accurate
- update docs/THANKS
- update `docs/THANKS`
- make sure all relevant changes are committed on the master branch
- tag the git repo in this style: 'git tag -a curl-7_34_0'. -a annotates the
- tag the git repo in this style: `git tag -a curl-7_34_0`. -a annotates the
tag and we use underscores instead of dots in the version number.
- run "./maketgz 7.34.0" to build the release tarballs. It is important that
@ -29,11 +30,14 @@ curl release procedure - how to do a release
- upload the 8 resulting files to the primary download directory
[data in the curl-www repo]
in the curl-www repo
--------------------
- edit Makefile (version number and date),
_newslog.html (announce the new release) and
_changes.html (insert changes+bugfixes from RELEASE-NOTES)
- edit `Makefile` (version number and date),
- edit `_newslog.html` (announce the new release) and
- edit `_changes.html` (insert changes+bugfixes from RELEASE-NOTES)
- commit all local changes
@ -43,11 +47,48 @@ curl release procedure - how to do a release
(the web site then updates its contents automatically)
[inform]
inform
------
- send an email to curl-users, curl-announce and curl-library. Insert the
RELEASE-NOTES into the mail.
[celebrate]
celebrate
---------
- suitable beverage intake is encouraged for the festivities
curl release scheduling
=======================
Basics
------
We do releases every 8 weeks on Wednesdays. If critical problems arise, we can
insert releases outside of the schedule or we can move the release date - but
this is very rare.
Each 8 week release cycle is split in two 4-week periods.
- During the first 4 weeks after a release, we allow new features and changes
to curl and libcurl. If we accept any such changes, we bump the minor number
used for the next release.
- During the second 4-week period we do not merge any features or changes, we
then only focus on fixing bugs and polishing things to make a solid coming
release.
Coming dates
------------
Based on the description above, here are some planned release dates (at the
time of this writing):
- November 5, 2014 (version 7.39.0)
- December 31, 2014
- February 25, 2015
- April 22, 2015
- June 17, 2015
- August 12, 2015
- October 7, 2015
- December 2, 2015